A key constraint of the site is its location on previously undeveloped land within a green belt. The effect of the proposal on the green belt, including openness, character and appearance, also had to be addressed.

Tir Collective prepared a landscape mitigation strategy to reduce adverse landscape and visual impacts. This was supplemented with AVRs to illustrate the proposed development with mitigation planting in place.

Following the successful appeal, where Tir Collective provided landscape expert witness services, the appeal was allowed and planning permission was granted in December 2022.

Key Project Features

  • 320MW Battery Storage
  • Located in Green Belt
  • The Scheme was approved in December 2022